I have a flow that runs every hour, and now the “F...
# prefect-ui
k
I have a flow that runs every hour, and now the “Flow Runs” part of the prefect cloud UI is covered with this flow (future scheduled flow runs). Is there anyway to only show the next scheduled flow run, instead of all of them?
3
2
j
Hi @Kyle D - thanks for the feedback. You can't currently hide all but one run but you can hide all scheduled runs - I made a video about how to do that: https://prefect-community.slack.com/archives/CKNSX5WG3/p1665148595458219 If you've got ideas about taking it beyond that (for example possibly having a scheduled runs slot and showing all other runs) please do open a ticket in the prefect repo and give more details about your use case. We always appreciate customer ideas even if we can't action every one of them straight away.
k
👍 I will file a ticket
🙏 1
I have seen the “No Scheduled” view, but the problems I have with that are: 1. It’s not the default view so I constantly need to select it 2. It’s not available on the “Runs” tab view on “Flows” or “Deployments” pages (have to use the run states filter, and then select everything except scheduled, which is 7 states)
👍 2