I have a flow scheduled to run on the second weekday of October, but I don’t see it in the “upcoming runs” or upcoming schedule of the flow in the UI. Is this expected?
k

Kevin Kho

04/18/2022, 1:32 PM
The scheduler only makes the next 10 flow runs at a time so if you have more than 10 between now and then, then it wont create that flow yet. You can test the setup by doing a flow with 1 minute interval and then schedulelling something further out
m

Matthew Seligson

04/18/2022, 1:34 PM
Is this 10 flow runs per flow or 10 flow runs across all flows? I have no other flow runs scheduled for this flow except for the October run.
k

Kevin Kho

04/18/2022, 1:35 PM
Per Flow. If that’s the case, you should see it. Is the schedule turned on?
m

Matthew Seligson

04/18/2022, 1:37 PM
Ah. We registered it with a schedule but set_schedule_active=False
So I turned it off and on again :)
k

Kevin Kho

04/18/2022, 1:37 PM
Ah ok nice!