How are mapped tasks billed in new model? As one task or as the size of the mapped task list?
n
nicholas
03/31/2021, 4:45 PM
Hi @Andrew Hannigan - mapped tasks are billed in the same way as other tasks; you're billed only for successful task runs whose duration is greater than 1 second.
a
Andrew Hannigan
03/31/2021, 4:46 PM
Got it - and if a mapped task was mapping over a list of 100 items, that would be billed as 100 tasks correct?
n
nicholas
03/31/2021, 4:47 PM
That's correct
nicholas
03/31/2021, 4:47 PM
The distinction here is between task runs and the tasks themselves - you're writing just a single task but the orchestrator is running 100 runs of that task