h

    Hugo Shi

    1 year ago
    With prefect cloud - is there a way to prevent overlapping flow runs?
    Kevin Kho

    Kevin Kho

    1 year ago
    Hey @Hugo Shi, yes using Flow Run Concurrency where if set a limit on that label of 1, then the next flow would wait for the currently running one to finish before starting
    h

    Hugo Shi

    1 year ago
    thank you!
    Ben Muller

    Ben Muller

    1 year ago
    Hey @Kevin Kho - further to this question is it possible to specify a
    superset
    for the task concurrency limit?
    This could be super useful
    Kevin Kho

    Kevin Kho

    1 year ago
    Wouldn’t that be the same if you have tag A,B, and C, and then A is a superset of B and C. All you need to do is set a limit on A along with setting B or C? And then apply limit on A and B to the Flow?
    Ben Muller

    Ben Muller

    1 year ago
    you are right lol. It is Monday morning here, excuse me lol