Hi folks, since around the past week (not exactly sure when this started) but the timeline started showing our mapped tasks as a single dot instead of an extended line
Marwan Sarieddine
03/17/2021, 3:07 PM
by that I mean - it now shows the mapped tasks while they are running like this
Marwan Sarieddine
03/17/2021, 3:08 PM
but for some reason only when the mapped tasks are finished, the line is shown correctly …
n
nicholas
03/17/2021, 3:08 PM
Hi @Marwan Sarieddine - thanks for reporting this, let me look into this and get back to you; I'll open a ticket if I can reproduce.
m
Marwan Sarieddine
03/17/2021, 3:08 PM
thank you !
n
nicholas
03/18/2021, 3:26 PM
Following up: I've found the issue and should have a fix out in the next release 👍