Hello, I would like to know if it is possible to assign an agent label when I create a schedule using the UI. When I create the schedule, the runs don't run because it doesn't have an agent label assigned
k
Kevin Kho
01/25/2022, 6:37 PM
Hi @Diego Oliveira, I am a bit confused why the agent label would be related to the schedule. The agent label needs to go on agent creation. The Flow label needs to go on the flow side (storage, not schedule). Does that help?
d
Diego Oliveira
01/25/2022, 7:08 PM
Its because I have multiple agents and I want to create a schedule associate with a agent, it's possible?
k
Kevin Kho
01/25/2022, 7:11 PM
It’s not but I think in Prefect 2.0 it might be possible because everything is tagged including Schedules