Hey! I have a task definition question for ECS
We have moved to push work pools (previously using agents). Really nice!
However, with the push work pools we don't seem to have an option to modify a task definition anymore? We can override the task definition ARN from the work pool when deploying, but then we need to generate one from scratch, which doesn't feel so nice. Is this correct? Is there a better way to do this?
And also specifying why we want to do this in case we are on the wrong track: We need to add a key in the existing task definition related to ephemeralStorage for one flow.