I've been looking at Automations to trigger a deployment based off of the completion of a flow run. But is it possible to trigger a deployment dependent on multiple different flow runs completing? I have two different flows, and it would be cool to start a deployment once both of those have finished, but not sooner. Is this possible?
1
n

Nate

09/15/2023, 5:42 PM
hey @Roger Dunbar - have checked out deployment triggers at all? here's an example that uses
flow.serve
but the same idea is possible with the worker / work pool deployment UX
🔥 1
r

Roger Dunbar

09/15/2023, 7:21 PM
@Nate this is just what I was looking for. Thank you!